Deccan Cable-Stayed Bridge, Pune Metro

Under construction

Pune
Our role: Structural 3D modelling and detailing
Bridges, Metro & Rail

Deccan Cable-Stayed Bridge, Pune Metro, engineering model Deccan Cable-Stayed Bridge, Pune Metro, under construction Deccan Cable-Stayed Bridge, Pune Metro, on completion
  • 136 mLength
  • 900 tCurved steel (approx.)

A 136 m curved, cable-stayed steel bridge across the Mutha River, linking Deccan Gymkhana Metro Station.

Owner
Pune Metro (Maha Metro)
Our role
Structural 3D modelling and detailing
Status
Under construction
Year
2023
Place
Pune
Sector
Bridges

The complexity

Nearly 900 tonnes of welded steel box girders, curved along their whole length and hung from high-tension cables. The cable anchorages, where all those forces meet the steel, were the hardest part.

How we simplified it

One parametric 3D model carried the changing geometry from end to end. We detailed every curved plate and every anchorage, and sent cutting-ready files straight to the fabricator.

Result

A new landmark for Pune, now under construction.

Technical details

For engineers: scope, numbers and codes.

ScopeStructural BIM and detailing of a curved, cable-stayed steel bridge: welded box girders from steel plate, cable anchorages, non-linear geometry, parametric modelling and CNC-ready outputs
NumbersAbout 900 t; 136 m long
Next projectTerminal Entrance, Surat AirportSurat, Aviation
Terminal Entrance, Surat Airport

Have something hard to build?

Send the drawings or the brief. We will come back to you.

Discuss your project